Residents: The following roads are scheduled to be milled and repaved as a part of this years road program. Revere Rd., High St., Unit (1-99) and 100 blocks of E. Washington Ave., unit and 100 blocks of S. Penn St., unit block of E. Broadway Ave., 100 block of E. Berkley Ave., 100 block of E. Madison Ave., Holly St. between E. Broadway and E. Berkley.
Work will begin with milling of the streets Tuesday morning September 23rd with paving beginning Wednesday afternoon or Thursday morning. We ask that the affected residents please remove their vehicles from the roadway by 7:00 am
All work is done weather permitting, so if we lose a day for rain, all work will be pushed back to the next day. The weather forecast for the work dates looks favorable so hopefully we can get through this without any delays.
The tentative schedule is as follows:
Revere Rd.-Mill Tuesday Pave Wednesday
High St.-Mill Tuesday Pave Wednesday
E. Washington Ave.-Mill Tuesday Pave Wednesday
S. Penn St.-Mill Tuesday Pave Thursday
E. Broadway Ave.-Mill Tuesday Pave Thursday
E. Berkley Ave.-Mill Wednesday Pave Thursday
Holly St.-Mill Wednesday Pave Thursday
E. Madison Ave.-Mill Wednesday Pave Thursday
A reminder that this is a tentative schedule as circumstances may change for many uncontrollable reasons. We will do our best to keep you up to date with any changes as soon as it becomes available to us.
Thank you for your cooperation