****UPDATE****
In an effort to clarify the milling and paving schedule, please see below . . .
On Thursday, September 7 we intend to mill in the following order:
South Church Street – #118 South Church Street to West Madison
400/500 Block of South Church, Willowbrook and 400/500 Block of Cherry Street
West Berkley Avenue – Cherry Street to South Church Street
On Friday, September 8 we intend to mill in the following order:
Academy Road – South Church Street to Cherry Street
West Madison Avenue – South Church Street to Contis Garage
Chester Avenue – West Madison Avenue to Cul-de-Sac
On Monday, September 11 we will pave in the following order, weather permitting:
West Berkley Avenue – Cherry Street to South Church Street
South Church Street – #118 South Church Street to West Madison
Academy Road – South Church Street to Cherry Street
Chester Avenue – West Madison Avenue to Cul-de-Sac
On Tuesday, September 12 we will pave in the following order, weather permitting:
400/500 Block of S Church, Willowbrook, and 400/500 Block of Cherry Street
West Madison Avenue – South Church Street to Contis Garage
The next set of streets, if above completed as above schedule:
Wednesday, September 13 – Mill in the following order:
N Sycamore Avenue – N Springfield Road to #131
Summit Street – N Springfield Road to Funeral Home
W Wyncliffe Avenue – #305 to Austin Drive
Austin Drive – N Springfield to W Wyncliffe
North Glenwood Lot
Thursday, September 14 – Pave in the following order:
N Sycamore Avenue – N Springfield Road to #131
Summit Street – N Springfield Road to Funeral Home
W Wyncliffe Avenue – #305 to Austin Drive
Austin Drive – N Springfield to W Wyncliffe
North Glenwood Lot
Thank you,
_______________________________________________________________________________________________________________________________________________
Residents of the 100 to 500 blocks of S. Church St., 100 block of W. Berkley Ave., 400 to 500 blocks of Cherry St., Academy Rd., W. Madison Ave., Willowbrook Rd., and Chester Ave.
The borough’s 2023 road program will be repaving all of the roads in the borough that were affected by the PECO gas main work over the past year. On the roads listed above the milling is scheduled to take place on September 6th & 7th, and the paving to follow on the 8th & 11th. The milling will take place rain or shine, while the paving is subject to change depending on the weather. you should have received a letter from the borough on August 31st detailing the scope of the work, if you did not you can click on the links below to view the letter.
If there are any changes to the posted schedule please check our website cliftonheightspa.gov where we will update any delays in the completion of the work.
Also residents of Austin Dr., N. Sycamore Ave., and Summit St. we did not forget about your streets. As soon as the previously mentioned streets are completed the crews will be moving onto your streets. We did not set the dates yet in case of weather holding up the aforementioned work. As we get through the first section of the paving we will update you through both a letter and through the website on which days we expect the milling and paving to take place on your streets.
If you have any questions or concerns you can call borough hall at (610) 623-1000 and someone will be glad to answer your questions.